CONSTRUCTION PHOTOS FROM
02-18-99
TO 04-08-99
|
 |
 |
Installation of the stairwell door in the vestibule
is completed and final trim work is installed.
(image taken on 02/22/99) |
|
 |
 |
Installation of remote controlled security cameras
is completed on the heliport. Video displays are installed in
M.E.R.S. Control and Security to monitor the heliport status.
(images taken on 03/05/99) |
|
|
 |
Railings are installed in the heliport stairwell and
the heliport deck is painted with markings.
(images taken on 03/09/99 and 04/05/99) |
|
|
 |
Final signage is installed throughout the heliport
vestibule and cabinets to hold personal protective equipment
are mounted on the vestibule walls.
(images taken on 04/08/99) |
|